Manufacturing Cost Reduction of Pressure Vessel - Case Study

CaseStudyPhotoChallenge:

To alter the product design prior to production launch to decrease the cost

Solution:

Altered weld joint design to greatly reduce construction man hours required to build

Reason:

A new pressure vessel was being developed for the market, but the build-hours were outside of the budget.  An improved design for manufacturing was needed to lower the cost.

Result:

Forty eight (48) man hours removed from the cost of each unit. The design of the pressure vessel water jacket was altered, which not only reduced size and weight, but also removed days of manufacturing cost without sacrificing performance

Read More Case Studies                          Capabilities        |        Products        |        Markets

 

 

Hornet’s Certifications

h-Stamp asme_hlw ASME-U-Stamp R-Stamp
nb_stamp china_certification_for_boilers

Click Icons to View Hornet's Certifications

Why Choose Us

When you absolutely, positively have to get it right the first time, on-time, on-budget, choose Hornet:
  • Quality & Customer Service
  • Improve YOUR Profitability
  • Development & Prototyping
  • High & Low Volume Production
  • Degreed Welding Engineer
  • Stainless Steel Capability
  • Boiler Stamps/Approvals
  • Certified Welding Engineers
  • In-house Processes
  • Trouble Shoot & Repair Capability
  • Warranty & Insurance Service
  • Complexity of Parts
  • Code Shop

Welds & Fabrications for:

  • Boilers
  • Oil & Gas
  • Automotive
  • Chemical
  • Acids & Caustic Substances
  • Filtration
  • Military
Read More